EVM Calculator

Estimate at Completion (EAC) Calculator

Forecast the total cost of your project given current performance. The most common formula assumes today's cost efficiency continues: EAC = BAC / CPI. The calculator also reports projected variance at completion (VAC).

Last reviewed: 3 May 2026 · Source: Project Management Institute, The Standard for Earned Value Management

EAC = BAC / CPI
N/A
Enter values
VAC = BAC − EAC
N/A
Enter values

The three EAC formulas

FormulaWhen to use
EAC = BAC / CPIDefault. Current cost performance is expected to continue for remaining work.
EAC = AC + (BAC − EV)Atypical. Current variance is a one-off; remaining work follows the original plan.
EAC = AC + ((BAC − EV) / (CPI × SPI))Pessimistic. Both cost and schedule performance are expected to continue.

Worked example

A software project has BAC = $100,000. After 3 months it has earned EV = $35,000 against AC = $38,000.

The project is forecast to overrun the original budget by about 8.6 percent if current efficiency continues. Use the CPI Calculator to drill into cost efficiency, or the full EVM Calculator for all 8 metrics together.

Common mistakes when computing EAC

Frequently asked questions

What is Estimate at Completion?

EAC is the forecasted total cost of a project given its current performance. It replaces the original BAC as the working forecast once the project is underway and actual data is available.

What does a negative VAC mean?

VAC = BAC − EAC. A negative VAC means EAC exceeds BAC — the project is forecast to overrun its original budget. Positive VAC is a forecast surplus.

Is EAC the same as ETC?

No. EAC is the forecast total project cost (past + future). ETC is only the cost remaining from now to completion: ETC = EAC − AC.

Can EAC be lower than BAC?

Yes. If CPI is greater than 1.0, the project is delivering more value than its cost, and EAC = BAC / CPI is below the original budget — a forecast surplus.

How does EAC tie to TCPI?

TCPI tells you the cost efficiency required on remaining work to finish at the original BAC (or at the EAC). If TCPI is above 1.0, it is a warning that the team must outperform the original plan to avoid overrun.

Related references

Disclaimer: This calculator is provided as an educational reference. It is not professional project management or financial advice. Always verify results against your organization's project controls policies and the latest PMI / PMBOK guidance.